By: MU Events Posted: 2019-02-11

Mashreq University City

Press office at Mashreq University visits Mashreq University City project in order to report the latest developments in the project. The Project Manager Mr. Amir Al-Tom said:
Now the work is underway on the three large halls complex with a capacity of 500 students each in addition to 4 small halls with a capacity of 200 students. While the ceiling of the first grand hall was poured, work continues on the beams and the ceilings of the other two remaining halls. The middle halls complex and the conference buildings were designed and ready for the construction during the next phase.